Project / 01

Project Einstein Peterborough

McCormick & Co’s new 93,000 m² factory and office development is a major food-production facility designed as a future net zero carbon building, where EcoAer installed the ventilation ductwork.

Location
Peterborough
Sector
Industrial
Client
McCormick & Co’s
Completed
Full System
Ecoaer scope
Ventilation, Louves, diffusers, insulation
Replace with main Ecoaer project image
01 / Project overview

Engineered around the building.

Built on a 9.49-hectare site, the new facility combines large-scale spice production with modern office accommodation and was developed with a strong focus on energy efficiency and sustainability.

Units / zones
Industrial
Project area:
Facility
Systems installed: 
Full ventilation system
Delivery programme:
OFficial installer
02 / The brief

What the project needed.

The building required a large, well-coordinated ductwork installation capable of supporting ventilation across extensive factory and office spaces while fitting within the wider low-carbon building strategy.

03 / Ecoaer's response

How the system was delivered.

EcoAer installed the ventilation ductwork throughout the facility, coordinating the system across the production and office areas as part of the building’s mechanical services installation.

04 / Technical scope

Project data.

System type
Large-scale industrial and commercial mechanical ventilation system.
Ecoaer services
Installation of the main ventilation ductwork serving the factory and offices.
Air distribution
Air was distributed through an extensive ducted network designed to serve the different environmental requirements of production and office areas.
Special requirements
The large scale of the facility, food-production environment and ambition for a net zero carbon building required efficient coordination, high-quality installation and integration with energy-conscious building services.
05 / Delivery
01

Design & review

System selection, drawing review, coordination and technical input.

02

Coordination

Integration with architecture, structure, electrical, ceilings and other services.

03

Installation

Site delivery, installation, quality control and programme management.

04

Commissioning

Balancing, testing, verification, client handover and ongoing support.

06 / Outcome

“A coordinated ventilation solution delivered to specification, commissioned for performance and integrated cleanly within the finished building.”

The result.

EcoAer delivered the ventilation ductwork for a major modern manufacturing facility, supporting effective air distribution while contributing to the wider building services strategy of the low-carbon development.